AHM WOLLONGONG
Client
Key Features
- Demolition of existing carpark
- Bulk and detailed excavation
- Detailed excavation for in-ground services
- Construction of in-ground footings
Referees
- Peter Orton
Bovis Lend lease
T:
0411 037 349
Description of Works
- This project was primarily a bulk excavation in the heart of Wollongong in extremely high strength rock – greater than 100MPa.
- Large diamond saws were used to saw-cut the perimeter of the site, and to create weakened plains to make hammering of the rock possible.
- Despite the difficulty of the site conditions the project was handed over within programme